background top icon
background center wave icon
background filled rhombus icon
background two lines icon
background stroke rhombus icon

Download "El túnel más grande del mundo: mineros frente a las montañas"

input logo icon
Video tags
|

Video tags

reportage
documentaire
enquête
forage
route
interview
témoignage
construction
Lyon
Turin
Italie
souterrain
voie
accès
chantier
travaux
insolite
chariot
rail
galerie
ouvrier
métier
risque
danger
sous sol
effondrement
projet
véhicule
train
voie ferrée
chemin de fer
casque
EPI
machine
engin
artificier
difficulté
destruction
environnement
nature
mine
mineur
pierre
roche
géologie
tunnelier
logistique
perceuse
yt:cc=on
Subtitles
|

Subtitles

subtitles menu arrow
  • ruRussian
Download
00:00:02
For millennia,
00:00:04
the tunnels allow us to shorten distances
00:00:07
and cross natural barriers like the mountains.
00:00:12
Today, in the heart of the Alps,
00:00:14
hundreds of men and women,
00:00:15
put their know-how at the service of a titanic project.
00:00:20
Build the biggest tunnel railway in the world,
00:00:22
the Lyon-Turin.
00:00:24
- Digging this tunnel is more complicated than the Channel Tunnel.
00:00:28
Within a pharaonic construction site,
00:00:30
these builders invent and test all the techniques,
00:00:33
to conquer the mountain
00:00:35
and build the work of the century.
00:00:37
- We are always in the process of modify, adapt, repair, maintain.
00:00:42
- The mountain will decide and we, we will adapt to the mountains.
00:00:45
In the depths, one of the machines the most powerful in the world,
00:00:48
a tunnel boring machine, digs through the toughest terrain in the massif.
00:00:53
- It is extremely rare to have such powerful machines.
00:00:57
Alongside this metal monster,
00:00:58
engineers, geologists and miners,
00:01:01
accomplish daily feats,
00:01:03
thanks to an arsenal of unusual machines.
00:01:09
In a dangerous environment,
00:01:10
they must identify the nature of the ground before each advance.
00:01:14
Call on the best pyrotechnicians,
00:01:16
to pierce the galleries the most complex,
00:01:19
while constantly evacuating,
00:01:21
millions of tons of rock thanks to a sprawling carpet.
00:01:24
- If we don't evacuate, we can't dig.
00:01:26
- We are at a flow rate of approximately 1,200 tonnes of material,
00:01:30
excavated per hour.
00:01:31
During four years of construction,
00:01:33
these extreme miners noted all the challenges,
00:01:36
technological and logistical,
00:01:37
to fulfill a strategic mission,
00:01:39
lay the first foundations of a work,
00:01:42
destined to endure through the ages.
00:01:45
We take you into the bowels of the most complex project
00:01:48
and the most ambitious in Europe,
00:01:50
the Lyon-Turin tunnel.
00:01:58
Invisible but essential,
00:02:00
the tunnels are among the works the most complex
00:02:03
and the most dangerous to build.
00:02:06
In the center of the Alps,
00:02:07
this valley is a crossroads strategic road,
00:02:10
one of the few crossing points between France and Italy.
00:02:14
Each year, more than 2.5 million heavy goods vehicles pass through the region.
00:02:21
To unclog these roads,
00:02:22
a titanic project has been launched.
00:02:25
Dig the biggest tunnel never made in the world,
00:02:27
the Lyon-Turin.
00:02:32
Located in the heart of Europe, this tunnel 57 and a half kilometers,
00:02:35
will be the longest gallery railway in the world.
00:02:40
It will be composed of two tubes distinct 11 meters in diameter,
00:02:43
connected every 300 meters through interconnections.
00:02:49
In total, 160 kilometers of underground,
00:02:52
must be built across the Alpine massif.
00:02:56
This buried megastructure,
00:02:58
will be the central work of the future high speed line,
00:03:00
between Lyon and Turin.
00:03:04
The tunnel could ease traffic of the Alps of more than a million,
00:03:07
heavy goods vehicles with piggybacking.
00:03:14
But here, the terrain is so difficult and unstable,
00:03:17
what building this tunnel represents a real feat.
00:03:21
- This tunnel is much more complicated than the Channel Tunnel.
00:03:25
The biggest difficulty of this project, and that's what makes it different,
00:03:28
of a classic tunnel site,
00:03:31
this is the geology encountered under the Alps.
00:03:34
We have a very heterogeneous geology, which evolves very often,
00:03:37
sometimes around ten from meter to meter,
00:03:40
we have a totally different geology.
00:03:42
The 1ʳᵉ stage of this project outside common is to confront each other,
00:03:45
to the most difficult area of ​​the massif,
00:03:48
by digging a reconnaissance gallery of 11.5 kilometers.
00:03:53
This 4-year strategic phase will determine the feasibility
00:03:56
and the future of the whole work.
00:04:04
Over the 160 kilometers planned galleries,
00:04:06
geologists have identified an area especially critical in the massif.
00:04:11
For 11.5 kilometers, rocks extremely hard are alternated,
00:04:15
with much softer rocks.
00:04:18
This is a section extremely complex,
00:04:20
that must be pierced by all means before going further.
00:04:24
For 4 years, each stage of this crucial mission,
00:04:27
was a real tour de force within of one of the largest construction sites in Europe.
00:04:32
A construction site to be organized extraordinary logistics,
00:04:35
on an unprecedented scale and whose numbers make your head spin.
00:04:40
For about fifteen kilometers, on the mountainside
00:04:43
and in the heart of his bowels,
00:04:45
400 people take turns night and day, seven days on seven.
00:04:49
An incessant ballet of trucks and super-powerful machines.
00:04:53
By tens of thousands,
00:04:54
gigantic prefabricated elements are lined up like on parade,
00:04:58
ready to reach the depths.
00:05:02
A sprawling carpet crosses the mountain and the valley,
00:05:05
in order to transport hundreds tons of rubble every hour.
00:05:11
Concrete is poured by the hundreds thousands of cubic meters
00:05:15
and tested every day in the laboratory.
00:05:17
The site even has its own water treatment plant.
00:05:25
And underground, under several hundreds of meters of rocks,
00:05:28
miners use machines unusual and oversized,
00:05:31
to dig the Alpine massif.
00:05:37
The conductor of this excessive logistical organization,
00:05:41
It’s Florent Martin.
00:05:45
- Since the start of our excavations, we met,
00:05:48
a multitude of events,
00:05:51
more or less important,
00:05:52
but who each time necessary the establishment,
00:05:55
special techniques and know-how.
00:05:59
To cope in all situations,
00:06:02
the teams apply a rigorous process.
00:06:04
Dig the mountain meter by meter,
00:06:06
evacuate thousands in parallel tons of rubble
00:06:09
and produce in tight flow the foundations of the future tunnel.
00:06:16
These extreme miners use everything an arsenal to tame the mountain,
00:06:20
notably an unusual tool.
00:06:24
- Here, we use a tunnel boring machine,
00:06:25
which can be related to a large drill.
00:06:27
All our teams are inside the wick
00:06:30
and we move forward with our fuse through the rocky material.
00:06:34
This giant tunnel boring machine is in charge of most of the digging.
00:06:38
9 kilometers out of the 11.5 to be completed.
00:06:42
To discover this mysterious drill,
00:06:45
you have to rush into the depths of the mountain,
00:06:47
in an environment totally out of the world.
00:06:51
After 3 years of digging at one speed average of 15 meters per day,
00:06:55
the machine traveled 8 kilometers.
00:07:01
Here is the tunnel boring machine called Federica.
00:07:08
When we go inside of this colossus of metal,
00:07:11
it's hard to imagine its size,
00:07:13
as the machine becomes one with the mountain.
00:07:19
Bigger than a football field with its 138 meters long
00:07:23
and as high as a 4-story building,
00:07:25
with its 11 meters in diameter,
00:07:27
this tunnel boring machine weighs 2,300 tonnes.
00:07:31
At the front of the machine,
00:07:33
the wheel that breaks the rock accumulates 300 tonnes.
00:07:37
Just behind, the steel cylinder which protects the machinery,
00:07:40
weighs 1000 tonnes, the equivalent of more than 800 cars.
00:07:47
This tunnel boring machine is also the most powerful in the world.
00:07:49
Federica is propelled by 14 engines,
00:07:52
350 kW each,
00:07:54
that is to say the equivalent of 8 Formula 1 at full throttle.
00:07:59
This power allows it to dig 15 to 20 meters per day,
00:08:03
to evacuate the rock while assembling the foundations of the tunnel.
00:08:07
- It's a machine which was oversized,
00:08:10
since we evolve in a context complicated geological, uncertain,
00:08:13
linked to large covers.
00:08:15
And so we oversized the machine,
00:08:18
both from a thrust cylinder point of view than in terms of motorization.
00:08:21
It is extremely rare to have such powerful machines.
00:08:26
Locked under more 800 meters of mountain,
00:08:29
or even 2,000 meters in places,
00:08:31
the tunnel boring machine must always move forward, no matter the cost.
00:08:36
- There is no reversing possible and moreover,
00:08:39
the faster we advance, the more we move forward steadily,
00:08:42
the easier it is to excavate.
00:08:45
Pierre-antoine Davanne is the engineer in charge of Federica.
00:08:48
He followed its design, its manufacturing, his first meters
00:08:52
and he manages the daily operation of this underground monster.
00:08:57
His adventure began 4 years ago previously, at the beginning of 2016,
00:09:01
when the tunnel boring machine arrived at the construction site.
00:09:10
The very first challenge of this mission is logistical.
00:09:13
How to get to the heart of the mountain such disproportionate elements
00:09:16
and heavy than the parts of a tunnel boring machine?
00:09:19
A journey as delicate as it is meticulous for around a hundred trucks.
00:09:30
But these are the last meters which were the most difficult.
00:09:34
The biggest convoys have descended over 2.5 kilometers,
00:09:37
in reverse, without visibility,
00:09:40
while the big packages passed a few centimeters away,
00:09:43
walls of existing underground spaces.
00:09:45
A dangerous maneuver who takes it alone,
00:09:47
a good two hours per element.
00:09:51
The pieces were placed in a cavity the dimensions of cathedrals,
00:09:54
over 24 meters high and 45 m long,
00:09:57
for the next step, assembly.
00:10:03
The machine head first been assembled with the front wheel,
00:10:06
who breaks the rock, then its steel envelope
00:10:11
and motorization,
00:10:12
before setting up the 7 essential trailers,
00:10:16
in operation of this buried factory.
00:10:19
After eight months of assembly and testing,
00:10:21
the tunnel boring machine is finally ready.
00:10:24
Ready to dig.
00:10:30
In spring 2019, the Federica tunnel boring machine,
00:10:33
begins the ninth kilometer of its reconnaissance mission.
00:10:39
To understand how this machine pierces the mountain,
00:10:42
you have to slip through a maze stairs and walkways,
00:10:45
to access the front, a few centimeters from the rocky front.
00:10:51
- We cross the shield and we arrive at the level of the cutting wheel,
00:10:55
this structure here and the terrain is really just ahead.
00:10:58
It’s a bit like the heart of the machine. because in fact,
00:11:01
all equipment available to the machine,
00:11:03
in the end, it still serves to make turn the cutting wheel,
00:11:07
exert pressure on the ground,
00:11:10
shatter the rock and route it outside the tunnel.
00:11:15
In a terrible commotion and an incessant trembling,
00:11:18
each digging phase lasts about thirty minutes.
00:11:22
30 minutes to grind precisely a 1.50 m of rocks,
00:11:25
under the suit of two phenomenal forces,
00:11:28
the horizontal thrust of the machine
00:11:30
and the rotation of its front part.
00:11:36
Of these 11.26 m in diameter,
00:11:39
the cutting wheel of the Federica tunnel boring machine,
00:11:41
is equipped with 76 dials,
00:11:42
50 cm ultra-resistant,
00:11:45
galvanized steel and tungsten carbide.
00:11:50
Oriented at a specific angle,
00:11:52
these discs act like blades which fracture the terrain,
00:11:55
pressing and turning on the rock.
00:12:00
As progress progresses,
00:12:01
the debris is collected by openings and buckets,
00:12:04
located on the sides of the wheel in order to be directed,
00:12:07
on a mechanical belt and evacuated at the rear of the tunnel boring machine,
00:12:10
then towards the surface.
00:12:14
In technical terms, we're talking about pickling.
00:12:18
This evacuation of the rock is one of the hotspots,
00:12:21
of the Lyon-Turin tunnel.
00:12:23
The challenge is immense.
00:12:25
Over the 11.5 kilometers,
00:12:26
approximately 1.3 million cubic meters of rock,
00:12:29
came out of the mountain.
00:12:31
If this mission succeeds, it is approximately 19 million cubic meters of stone,
00:12:35
which will have to be evacuated,
00:12:37
the equivalent of a mound 270 meters wide
00:12:40
and 1,000 meters high.
00:12:42
- We are at a flow rate of approximately 1,200 tonnes,
00:12:44
of material excavated per hour.
00:12:47
So 1200 tonnes of materials,
00:12:50
it is the equivalent 120 trucks per hour,
00:12:52
that must be managed and treated.
00:12:57
From the tunnel boring machine, several kilometers from the surface,
00:13:00
a large rubber band unfolds gradually,
00:13:03
as the machine moves forward.
00:13:07
This belt transports the debris to the speed of 1,200 tonnes per hour,
00:13:11
up to a buffer zone where they are stored,
00:13:13
in large tanks, the hoppers,
00:13:16
before being directed towards another carpet,
00:13:18
who evacuates them at speed 800 tonnes per hour,
00:13:21
to the surface,
00:13:22
then finally to the sorting site,
00:13:25
three kilometers further.
00:13:29
In total, the conveyor belt,
00:13:31
is a sprawling infrastructure which extends for nearly 15 kilometers.
00:13:36
With such a distance, the risks of breakdowns are multiplied.
00:13:40
- It's huge, we see construction sites in Greater Paris,
00:13:43
Greater Paris, Tunneling, the belt, the conveyor,
00:13:46
at worst, he will do 2, 3 or 4 kilometers...
00:13:49
And not under these conditions,
00:13:52
on the climbs, the descents, the turns...
00:13:56
This is really technical.
00:13:59
David Demiere, the person responsible for the conveying,
00:14:02
spends his days settling new urgent problems.
00:14:10
Today a hole was spotted on the carpet.
00:14:13
Vulcanization must be carried out,
00:14:15
that is to say a kind of welding between two pieces of rubber.
00:14:20
Nothing very difficult, but time is running out,
00:14:22
because the digging must resume as quickly as possible.
00:14:26
- If we don't evacuate, we can't dig.
00:14:30
It's clear, since otherwise we will bury ourselves,
00:14:32
we're going to be a mole!
00:14:36
Just outside the tunnel, all debris removed,
00:14:39
pass through a sorting zone before to be separated further down the valley.
00:14:43
This is the domain of the geologist, Anaïs Barel.
00:14:48
- The materials are analyzed by these two devices.
00:14:51
Then these two devices decide,
00:14:53
of the final destination of the materials.
00:14:57
These two devices are optical devices,
00:14:59
able to precisely identify the nature of the rock.
00:15:04
A first camera first analyzes the dominant color of the spoil.
00:15:08
A second camera scans then the stones
00:15:11
and determines their size in real time.
00:15:15
The results of these analyzes are transmitted 3 kilometers further,
00:15:18
at the very end of the conveyor belt which crosses the valley.
00:15:23
On the deposit site,
00:15:25
these gigantic articulated bridges, called locusts,
00:15:28
orient the stones according to of their qualities.
00:15:33
Dark and thin materials of carbonaceous origin,
00:15:35
are separated from larger materials and lighter, like sandstone,
00:15:38
which will be reused or recovered, as they say in the jargon.
00:15:46
- Classified materials in the non-recoverable part,
00:15:49
are organic, carbonaceous.
00:15:51
They evolve over time and we will not be able to reuse them.
00:15:54
However, recoverable materials,
00:15:56
have good characteristics chemical and mechanical.
00:15:59
We will have materials stronger
00:16:02
and with better resistance.
00:16:05
Rock debris too fragile are stored as inert waste.
00:16:09
But the strongest materials,
00:16:11
will be reused on the construction site,
00:16:13
especially for making concrete and to build the enormous embankments,
00:16:17
on which the rails will pass of the future Lyon-Turin train line.
00:16:22
The goal is to excavate materials, to reuse them,
00:16:25
to make a loop.
00:16:26
Its very important because it will allow us,
00:16:29
to reuse our own materials, economically or ecologically,
00:16:33
this is a very important issue.
00:16:36
Organize this gigantic evacuation circuit,
00:16:39
is a challenge for these rock specialists.
00:16:47
But inside the mountain, another challenge awaits them.
00:16:50
Determine in advance the nature rock to drill.
00:17:01
Every 2 days, the tunnel boring machine stops digging for a few hours,
00:17:05
in order to carry out a strategic operation,
00:17:07
a recognition survey.
00:17:14
At the front of the machine,
00:17:16
sturdy metal rods are deployed across the shield,
00:17:19
to pierce the rocky front.
00:17:23
Under the effect of ultra-rapid rotation and violent percussion,
00:17:26
the serrated end of the rod comes to crush the rock.
00:17:31
The metal bar is extended gradually,
00:17:34
to sink up to 50 meters in front of the tunnel boring machine.
00:17:42
Debris is evacuated thanks to with water under pressure.
00:17:48
Like gold prospectors with their sieve,
00:17:50
geologists spring into action.
00:17:54
They analyze the rock debris in order to to know what types of terrain,
00:17:58
present themselves in front of the tunnel boring machine
00:18:00
and anticipate possible delicate passages.
00:18:09
To know the mountain even more precisely,
00:18:12
several large samples span are practiced,
00:18:15
as progress is made.
00:18:20
These extractions are called,
00:18:22
exploratory core drilling.
00:18:30
- We put a hollow diamond crown.
00:18:32
We are going to put a first stem,
00:18:35
it's going to turn around quickly, it's like a circular saw,
00:18:38
as we push and it turns,
00:18:41
the carrot will come in in a hollow tube.
00:18:44
And once we're 1.50 m,
00:18:47
we're going to extract this carrot and get it back,
00:18:49
so that we we can analyze it.
00:18:53
On these samples, geologists observe the structure of the stone,
00:18:57
its fractures, in order to determine the nature of the rocks encountered,
00:19:01
throughout the mission of recognition.
00:19:07
In forming the Alps, there are hundreds of millions of years,
00:19:10
the movement of the plates formed a immense millefeuille of rock layers,
00:19:13
very different.
00:19:17
We dig 800 meters underground,
00:19:19
in a geology which is both complex and a little uncertain.
00:19:23
So, we have to adapt, probe, recognize the terrain
00:19:27
and adapt in the way to dig.
00:19:30
- We ran into terrain which is the Carboniferous terrain.
00:19:34
Its particularity is to be a very changing terrain,
00:19:38
with smutty pasts
00:19:41
and clayey, flexible and convergent,
00:19:44
that is to say a piece of land who move
00:19:47
and which closes gradually and as we open it.
00:19:50
This mixed geological composition hard and soft rocks,
00:19:54
as well as rock covers more than 800 meters,
00:19:56
create important phenomena of convergence.
00:20:00
The dug hole immediately tendency to close,
00:20:03
under the pressure of the mountain.
00:20:06
This is mainly the case in a critical zone of 2.5 kilometers,
00:20:09
at the very beginning of the tunnel of recognition.
00:20:14
- The tunnel boring machine does not pass at this place, if we put one,
00:20:17
the ground would close in on him and the tunnel boring machine would be stuck.
00:20:25
While Federica continues her journey,
00:20:27
these very complex 2.5 kilometers are dug in parallel,
00:20:31
thanks to a completely different know-how.
00:20:37
In this gallery, it takes all the courage
00:20:39
and the ingenuity of miners who advance with explosives
00:20:42
and unusual devices.
00:20:48
- Here, we are in the base tunnel, of the Lyon-Turin tunnel.
00:20:52
Here, we are heading towards Lyon,
00:20:54
This is where we started digging.
00:20:56
And then we go towards Turin,
00:20:59
where we're going to join the game of the tunnel boring machine which is in front of us.
00:21:02
The part with the tunnel boring machine, we almost never see the rock,
00:21:05
she is in front of the shield, while we here,
00:21:08
it’s the terrain, it’s the mountain.
00:21:10
We dig directly into the rock, we are in constant contact,
00:21:13
with the rocky massif.
00:21:18
We are now on the platform exterior of the construction site,
00:21:21
in a somewhat remote area,
00:21:24
under guard, in the powder magazine.
00:21:29
Rémi Fortanété, the engineer in charge from the traditional site area,
00:21:33
and Hicham Ouarraq, a professional artificer,
00:21:36
prepare for the next blast.
00:21:40
The next volley as they say.
00:21:43
- For the cap, we will put two kilos for 1 m 20.
00:21:46
Slaughter, 1.5 kilo.
00:21:48
2.5 kilos, lifting
00:21:50
and 300 grams in cutting.
00:21:53
They come to select the right detonators,
00:21:56
for each zone of the shooting plan.
00:21:58
The concentration is maximum,
00:22:00
the slightest mistake could be fatal.
00:22:08
Every explosive digging follows the same process.
00:22:11
First of all, a Jumbo,
00:22:13
a huge tractor with three articulated arms,
00:22:15
comes to drill 190 holes 1.20 m deep,
00:22:18
in the rocky front.
00:22:27
These holes are then filled by 2 chemical emulsions,
00:22:29
contained in these tanks and whose mixture,
00:22:32
becomes explosive at the end of a few seconds.
00:22:39
The detonators are finally positioned,
00:22:41
then connected to the instrument firing,
00:22:44
located at a good distance, more than 50 meters away.
00:22:50
Once recharged with power electric manually,
00:22:53
it's the firing.
00:23:00
- In an explosion, it is energy that the material will transmit
00:23:05
to the rock that will come fracture the rock.
00:23:08
And that's how the rock will be able to break.
00:23:12
On the rocky front, the 190 charges explode
00:23:15
and release their energy in a specific order.
00:23:18
First in the central part in order to create a zone of fragility.
00:23:22
Then snail all around,
00:23:24
to widen the hole.
00:23:26
And finally on the ends to cut
00:23:28
the precise outline of the gallery.
00:23:32
To get the maximum damage,
00:23:34
the firing of the charges follows careful sequencing,
00:23:37
with a delay of 25 milliseconds per target area.
00:23:45
To explode a meter of rock eleven meters high,
00:23:49
it takes 8 hours of preparation
00:23:51
and 300 to 400 kilos of explosives.
00:23:55
But if the ground is too soft,
00:23:57
this mining method is not effective.
00:24:00
Then enters the scene a supercharged machine.
00:24:09
This machine is a BRH, a hydraulic rock breaker.
00:24:13
A 35-ton track equipped with with a nine-ton arm,
00:24:16
powered by pressurized water,
00:24:18
a great jackhammer.
00:24:22
At 2 BRH, it will take approximately 8 hours of work,
00:24:25
to excavate a meter of rock,
00:24:27
starting the attack with the bottom of the rocky front,
00:24:30
before gradually rising again.
00:24:35
Once the mountain is pierced,
00:24:36
this is the start of a new work cycle,
00:24:38
absolutely crucial for worker safety
00:24:41
and the progress of the tunnel.
00:24:46
We must strengthen and support as quickly as possible the walls,
00:24:48
before they collapse under the pressure from mountain movements.
00:24:55
After digging a meter,
00:24:57
the priority is to confine the rocky front
00:24:59
with a first layer of concrete,
00:25:01
then reinforce the contours from the gallery.
00:25:05
On the vault, twelve bolts of 8 m are inserted and sealed,
00:25:08
in order to maintain the rock superior in compression.
00:25:13
About forty new 8 m bolts are drilled,
00:25:16
all around the circumference,
00:25:18
in order to hang the metal plates which will block the rock.
00:25:26
These bolts are installed by a huge jumbo type tractor,
00:25:29
equipped with three articulated arms.
00:25:34
- First, the hole is stuffed with a jumbo,
00:25:36
with a drill bar.
00:25:38
Then we thread this bolt inside.
00:25:41
We connect a pump here
00:25:43
and then we inject water inside
00:25:46
and the bolt will expand
00:25:48
and take the entire diameter of the hole.
00:25:53
Once the bolts are installed and the metal plates fixed,
00:25:56
the support operation is far from complete.
00:26:01
The Jumbo is back.
00:26:04
This time he's wearing a huge metal frame,
00:26:06
that he will slowly deploy in the gallery.
00:26:10
- We're coming to put up a hanger.
00:26:13
He is closest to the field,
00:26:15
to accompany almost instantly ground movements.
00:26:19
Once the bolts are arranged in halo all around the cavity,
00:26:22
a large frame circular metal,
00:26:24
a hanger is positioned along the walls.
00:26:29
To absorb movements of the mountain without breaking,
00:26:32
the hanger slides in 8 different locations.
00:26:36
This support makes it possible to avoid collapses,
00:26:38
while adapting to ground movements.
00:26:45
The operation ends with the face of shotcrete.
00:26:50
With the remote-controlled spear, a fairly viscous concrete,
00:26:53
to hang well the wall is sprayed over the entire cavity.
00:27:00
2 large top trucks are necessary,
00:27:02
to build the latter coating layer.
00:27:07
With this type of support, we let the ground decompress,
00:27:10
we let him work as he wants.
00:27:12
It’s support.
00:27:13
And then the land, once it has took the place he wanted to take,
00:27:17
we accompany him and ultimately, we block it.
00:27:22
After installing the support,
00:27:23
topographers monitor every day possible deformations of the tunnel,
00:27:27
by pointing their laser at targets installed all along the wall.
00:27:31
These ultra-precise measurements allow to detect ground movements,
00:27:35
too important.
00:27:37
- There is an alert threshold.
00:27:39
We have an alert threshold 5 centimeters over 24 hours.
00:27:42
On the other hand, if we arrive at 5 centimeters over 24 hours, there,
00:27:44
you have to start worrying.
00:27:46
No matter the nature of the rock, the terrain is always in motion.
00:27:50
It is necessary to monitor and particularly in this area,
00:27:52
which is very bad.
00:27:55
The ground is so unstable that the topographers have measured,
00:27:58
unprecedented deformations in several places,
00:28:01
especially in an area where the underground closed,
00:28:04
70 centimeters in a few days.
00:28:08
But the foundations of metal and concrete stopped these movements,
00:28:11
without breaking thanks to their flexibility.
00:28:15
When these reinforcements are not sufficient,
00:28:17
to absorb ground movements,
00:28:19
miners superimpose new concrete rings,
00:28:21
80 cm thick and ultra-rigid.
00:28:25
- We encountered a geological fault,
00:28:28
we had a landslide with convergences which accelerated rapidly.
00:28:31
We had a landslide of approximately 700 cubic meters.
00:28:34
Here it is impossible to treat the land,
00:28:37
without blocking due to of this geological fault.
00:28:40
Here we really came make two rings,
00:28:44
so the first ring where here inside,
00:28:46
we came to make the formwork,
00:28:48
with a concrete pour behind
00:28:50
and then inside we came make a second ring,
00:28:54
in the same way,
00:28:55
with formwork inside and concrete.
00:28:59
In this very complex part 2.5 kilometers,
00:29:02
engineers and companions adapt their techniques,
00:29:05
depending on the terrain.
00:29:08
It is a titanic job which allows you to move forward at speed,
00:29:11
one meter per day.
00:29:19
A few kilometers further east,
00:29:20
the tunnel boring machine digs 15 meters per day towards Turin.
00:29:24
Less than three years after his departure,
00:29:26
he swallowed 8.5 kilometers,
00:29:28
out of the 9 of his mission of recognition.
00:29:33
During this journey, you must also protect men
00:29:36
and equipment against landslides.
00:29:39
The entire front part of the machine is reinforced by a robust shell
00:29:43
7 cm of steel.
00:29:45
It's the shield.
00:29:48
- It is a metal structure,
00:29:50
which weighs more than 1000 tonnes
00:29:52
and so that's the part the heaviest of the machine,
00:29:55
because this is where transit the greatest efforts,
00:29:58
to move the machine forward.
00:30:00
And this is where also transit significant efforts,
00:30:02
of the ground in the event of convergence,
00:30:05
or if a block was placed to fall on the shield.
00:30:09
But just behind this shield,
00:30:11
the ground could close
00:30:12
and you have to put it down very quickly solid foundations.
00:30:16
- So we meet difficult terrain,
00:30:20
very uneven and pushing.
00:30:23
So we had the need,
00:30:25
to dig and immediately put after digging,
00:30:28
a covering.
00:30:30
This covering is this immense concrete frame,
00:30:33
composed of thousands of successive rings.
00:30:38
A ring is made up of 9 elements which fit together
00:30:41
and which we call voussoirs.
00:30:46
Only two elements have a different shape,
00:30:48
the keystone that closes the ring
00:30:50
and the raft which forms the tunnel floor.
00:30:55
Each ring measures 1.52 m wide on one side
00:30:58
and 1.48 m from the other.
00:31:02
This slightly beveled structure allows you to correct the trajectory
00:31:05
and take turns.
00:31:10
The difficulty was to say,
00:31:12
are we able to put put these rings in place,
00:31:14
before the ground is closed on the machine?
00:31:17
And how were we going to make sure that these rings would resist
00:31:21
and resist efforts,
00:31:23
which will last 100 years?
00:31:28
The first challenge is to supply the construction site continues,
00:31:31
with a colossal number of rings.
00:31:34
Over the 9 kilometers recognition of the tunnel boring machine,
00:31:37
nearly 6,000 rings, i.e. 56,000 segments,
00:31:40
are necessary.
00:31:45
These are more than 400,000 tonnes of concrete and steel that must be manufactured
00:31:49
and install in three years.
00:31:53
- There we are in storage temporary of our segments,
00:31:56
which will feed,
00:31:58
the tunnel boring machine.
00:32:00
They were made a few kilometers from here,
00:32:02
in a specific factory
00:32:04
and are delivered by truck every day.
00:32:09
We are 2 kilometers from the construction site main, in the voussoir factory.
00:32:13
A specially rehabilitated place to produce in tight flow,
00:32:17
the foundations of the Lyon-Turin tunnel.
00:32:20
The manufacturing process is organized to keep pace,
00:32:23
ten complete rings per day,
00:32:25
i.e. 90 pieces weighing up to eight tons.
00:32:29
Here is the welding workshop where assembled the metal frames,
00:32:33
future voussoirs.
00:32:36
Each of them contains 120 kilos of steel.
00:32:38
This is more than double that which is used normally,
00:32:41
to construct buildings.
00:32:44
- A building that holds by its own weight,
00:32:46
it must hold up to the wind, to the snow, to the rain,
00:32:49
these are constraints relatively light,
00:32:51
compared to what we can have,
00:32:53
support of the ground on the complete ring, on the segment, therefore on the concrete.
00:32:57
The segment will hold the ground behind the tunnel boring machine, it will be compressed,
00:33:01
but in the compression efforts, there is also bending,
00:33:04
that's why there are steels inside to be able,
00:33:06
keep up this effort.
00:33:09
These metal carcasses join then the other part of the factory,
00:33:13
where 45 molds rotate in a great continuous merry-go-round.
00:33:17
Each of these molds is scrupulously checked.
00:33:20
Accuracy is crucial for the strength of the tunnel.
00:33:24
- We put all these pieces together,
00:33:27
to have the eight elements.
00:33:28
It has to fit perfectly one in the other,
00:33:32
otherwise it wouldn't work.
00:33:33
There should be no deformation because we would have joints, games
00:33:37
and at one point, bolting and the hanging of the rings,
00:33:39
or segments together would no longer work.
00:33:44
Once the steel reinforcement has been removed in its mold, comes the filling.
00:33:49
For the first 6,000 tunnel rings,
00:33:52
it takes about 165,000 meters concrete cubes.
00:33:55
Enough to build the equivalent of 1,500 houses
00:33:58
of 150 square meters.
00:34:04
Once filled and after a few strokes with a trowel,
00:34:07
the mussels then pass in huge ovens,
00:34:09
for cooking for 7 hours,
00:34:11
in order to accelerate the setting of the concrete.
00:34:16
When coming out of the oven, the segments have not yet reached,
00:34:19
their optimal strength.
00:34:22
They are stored for 28 days,
00:34:24
in order to dry and increase resistance.
00:34:29
- Every day, we do test tubes to check,
00:34:32
that the concrete we use is of good quality
00:34:34
and this resistance at 28 days.
00:34:39
These samples are tested in a small laboratory integrated into the site.
00:34:45
Here, the concrete is put to the test.
00:34:48
It is compressed, split,
00:34:51
exploded, in order to ensure that it is quite solid,
00:34:55
for the work.
00:34:56
In the tunnel, only one weak link,
00:34:59
could endanger the whole structure.
00:35:03
Once the segments reached maturity,
00:35:05
they are transported by truck at the entrance to the tunnel,
00:35:08
where they wait a strange new machine.
00:35:11
A huge lifting bridge comes place the concrete blocks,
00:35:14
on TSPs,
00:35:17
trains on tires.
00:35:19
About thirty meters long,
00:35:20
this 120-ton convoy rushes then in the mountain.
00:35:25
On the way to the tunnel boring machine,
00:35:26
after three years of digging,
00:35:28
he has nothing left only 500 meters to go,
00:35:31
to validate the following of the Lyon-Turin project.
00:35:34
The TSP has been specially designed to sneaking inside Federica.
00:35:39
This megamachine is not only able to pierce the mountain,
00:35:44
it installs at the same time the first 6,000 rings of the tunnel.
00:35:49
When a 30 minute cycle digging ends,
00:35:51
a new phase begins.
00:35:53
The different elements of the ring are sent in a specific order,
00:35:57
to the front of the machine under the shield.
00:36:01
From there, a gigantic articulated arm,
00:36:03
equipped with a powerful suction cup take over.
00:36:08
Its name, the voussoir erector.
00:36:13
The erector arm grab a piece,
00:36:15
then turns and unfolds,
00:36:17
in order to position every part in the right place.
00:36:21
Once in their place, the segments keep their position,
00:36:24
thanks to powerful cylinders until the ring,
00:36:27
is closed with its key.
00:36:29
The raft is then installed.
00:36:34
The installation of a complete ring lasts about twenty minutes.
00:36:38
It's a delicate operation,
00:36:40
because these immense blocks must be positioned to the millimeter,
00:36:43
to fit perfectly.
00:36:50
Once the segments are embedded,
00:36:52
the ring is installed and the tunnel boring machine,
00:36:54
can start a new digging phase.
00:36:57
- This concrete ring allows us security.
00:37:01
Then our tunnel boring machine comes to take support on this concrete ring,
00:37:04
to seek support and be able to push,
00:37:07
against the rock.
00:37:08
A tunnel boring machine is like when we ski to be able to turn,
00:37:12
to be able to move forward, to be able to turn,
00:37:15
you must be able to take support on something.
00:37:18
When we have no support, we cannot lead
00:37:21
and we can't move forward.
00:37:24
To propel yourself forward,
00:37:25
the machine activates its 44 cylinders of thrust which take directly,
00:37:29
their support against the last concrete ring installed.
00:37:33
The advancement of the tunnel boring machine allows then to eject this ring,
00:37:36
outside the shield.
00:37:41
There is one last operation left to complete the installation of the ring.
00:37:46
- The cutting wheel who digs the ground,
00:37:48
has a diameter of 11.25 m.
00:37:50
The concrete ring that we place,
00:37:52
has an external diameter of 10.80 m.
00:37:55
So that means that there is 45 cm of empty space,
00:37:57
between the ground and the concrete ring.
00:38:01
To fill this empty space,
00:38:03
engineers use a very innovative mixture.
00:38:09
Two fluid components are injected in parallel through the ring,
00:38:13
cement grout on one side and a setting accelerator on the other.
00:38:18
When the 2 products meet,
00:38:20
the mixture turns into a paste as strong as concrete,
00:38:23
in just eight seconds.
00:38:28
The work is now a body with the mountain.
00:38:32
These sturdy foundations block landslides
00:38:34
and absorb pressure phenomenal views of the massif.
00:38:39
Like a gigantic mechanical earthworm,
00:38:41
the machine alternates tirelessly the digging phases of 1.50 m
00:38:46
and break cycles to pierce the rock,
00:38:48
while building the foundations of the Lyon-Turin tunnel,
00:38:51
at a speed of 15 meters per day.
00:38:58
Protected by its work, the tunnel boring machine advance sheltered from landslides.
00:39:02
But these extreme miners must never relax.
00:39:07
On this disproportionate construction site,
00:39:08
every little detail counts.
00:39:10
Especially in the bowels of the mountain,
00:39:12
where the teams work in a hostile environment.
00:39:15
- There is a lot of humidity, there is heat.
00:39:18
The work is physical.
00:39:21
It's hard to stay 8 or 9 hours,
00:39:23
in this place, we get tired very quickly.
00:39:28
- You must never relax. We have not no slowdown phases,
00:39:32
where we can be,
00:39:35
less attentive or less demanding.
00:39:37
As soon as we relax,
00:39:39
it always translates to either technical problems,
00:39:42
either security problems, or both at the same time.
00:39:46
In these galleries buried by several kilometers from the surface,
00:39:49
the air is unbreathable and the unbearable heat.
00:39:52
It's almost 40 degrees.
00:39:55
The work would be impossible without this immense yellow sheath,
00:39:58
which overlooks the gallery.
00:40:00
It brings 50,000 liters of fresh air per second.
00:40:08
At the same time, the mountain rejects enormous underground water reserves.
00:40:12
To protect yourself from flooding,
00:40:14
an oversized infrastructure allows you to pump
00:40:17
and process between 150 and 1,000 liters per second.
00:40:22
But underground, the biggest fear is fire.
00:40:27
The tunnel is full of sensors nicknamed breathers,
00:40:31
allowing the detection of fumes flammable gases.
00:40:35
In case of fire,
00:40:36
these confined galleries fill up a few minutes of asphyxiating fumes
00:40:40
and you have to quickly join one of the survival chambers,
00:40:43
installed every 1,000 meters.
00:40:48
These hermetic boxes are equipped,
00:40:50
to stay confined in complete autonomy,
00:40:53
to around twenty people for 24 hours.
00:40:57
Digging the Lyon-Turin tunnel in this extreme environment,
00:41:00
is a daily challenge.
00:41:02
Few are those who can endure these conditions,
00:41:04
and even rarer are those who can,
00:41:06
pilot these underground colossi.
00:41:10
After 3 years of digging, there remains only a few hundred meters,
00:41:13
to drill for the tunnel boring machine.
00:41:18
The operation is controlled from the cabin control at the front of the machine,
00:41:22
a few meters just behind the wheel.
00:41:26
At the helm today, it's Pierre Gaspard.
00:41:30
This young pilot is capable to maneuver with skill,
00:41:32
this machine too monumental and powerful.
00:41:37
But how to go about it when we is as short-sighted as a mole?
00:41:46
The teams are on deck.
00:41:47
The conveyor belt is engaged, ready to evacuate the crushed rock.
00:41:51
The digging phase can now begin.
00:42:00
Minute by minute and millimeter by millimeter,
00:42:02
Pierre will play on the push and the rotation speed,
00:42:05
to constantly adapt to the rock.
00:42:09
- Currently, we are progressing at 40 mm/min,
00:42:11
depending on the terrain, we adapt.
00:42:13
If the ground is really very hard,
00:42:15
to avoid too much force on the machine,
00:42:18
we are going to reduce the speed.
00:42:20
If the marination is too great, if we don't have too much land,
00:42:24
we will reduce the speed to avoid to have problems behind on the mat.
00:42:31
To refine his driving, the driver monitors several parameters,
00:42:34
like the necessary power to break the rock,
00:42:37
or the rate of evacuation of debris.
00:42:40
The pilot is the first to see machine parameters.
00:42:44
He's the first to adapt to the geology encountered
00:42:47
and at the cadences that we must respect.
00:42:51
Excluding incidents, the tunnel boring machine is moving forward 12 to 15 meters per day.
00:42:56
He sometimes has spikes speed at 20 meters per day,
00:43:00
which is considerable in such complex terrain.
00:43:04
But in addition to keeping up the pace,
00:43:06
the pilot must also keep the correct trajectory.
00:43:12
- We have a laser sight which starts from a point,
00:43:15
that the topos, in the morning, put in place,
00:43:18
with laser sight who reaches the shield,
00:43:21
to give us guidance in real time,
00:43:23
which is calculated approximately every 30 seconds.
00:43:26
Following this, it gives us a trend vertical of the machine,
00:43:30
horizontal also from the inclination
00:43:32
and our destination on all the length of the route.
00:43:40
Over a distance of five kilometers,
00:43:42
the tunnel must not deviate its trajectory of more than 25 cm.
00:43:46
At each 1.50 m digging,
00:43:48
the margin of error is less than 50 mm.
00:43:51
This precision is all the more more important than in the long term,
00:43:54
it will be necessary that the two tubes of 57.50 kilometers,
00:43:57
are perfectly aligned.
00:44:02
- It's still very fine, the way of driving,
00:44:05
we can't give a turn abrupt, it's impossible.
00:44:07
We have trains who will pass later.
00:44:10
When we start to feel that the machine starts to leave,
00:44:13
we give trends and guidance
00:44:15
to the machine to bring it back in the right direction,
00:44:18
over a given distance, in order to avoid any angle,
00:44:21
any major departure from the machine,
00:44:24
who could also put her in difficulty.
00:44:28
Refine your thrust, control evacuation of rocks,
00:44:31
lay the foundations and stay the course.
00:44:34
Piloting this colossus underground
00:44:37
is a real daily feat.
00:44:46
This tunnel boring machine is specially designed to cross the hardest rocks.
00:44:50
On the front side of the machine,
00:44:52
the wheels that fracture the stone are made of tungsten carbide,
00:44:55
one of the materials the most resistant in the world.
00:44:59
But the rock is so hard that it you have to sneak inside
00:45:02
structure every day,
00:45:04
to check their level of wear.
00:45:10
- It is a phenomenon of abrasion.
00:45:12
We come to slam the rock, we force it
00:45:15
and we create abrasion on the dials.
00:45:20
These strategic pieces are regularly replaced.
00:45:22
A routine operation far from being trivial,
00:45:25
when each of them weighs almost 200 kilos.
00:45:30
But if we can repair the bit of this drill,
00:45:33
we cannot change it when the terrain is radically transformed
00:45:37
and becomes notably very tender.
00:45:41
- We have a tunnel boring machine. Once that we started to dig,
00:45:44
it will have to adapt to all the geologies encountered.
00:45:47
- For exemple, when using a drill,
00:45:50
when you put a wood wick, it works very well in wood,
00:45:53
but very badly in concrete.
00:45:55
A concrete drill bit that works very good in concrete,
00:45:58
but very badly in the woods.
00:45:59
We have a real fuse problem,
00:46:02
she must drill and in the wood and in concrete.
00:46:06
From the start of the construction site,
00:46:08
the rock of the Alps posed problems to the Lyon-Turin tunnel teams.
00:46:13
At the beginning of 2017, after a few weeks of digging,
00:46:16
the tunnel boring machine was stopped dead in its tracks.
00:46:22
He just entered a rift very friable geological.
00:46:26
- At 200 meters, we encountered a major flaw where our machine,
00:46:29
was confronted with conditions extreme geological conditions.
00:46:33
A completely unstructured area.
00:46:35
We had an accident which went far beyond,
00:46:37
of what we had imagined,
00:46:39
the ground had no hold,
00:46:42
we found ourselves in the situation where the land came from
00:46:46
and the machine was no longer moving forward.
00:46:50
In this geological fault, the tunnel boring machine is slipping
00:46:52
and his wheel fills with a blackish mud,
00:46:55
impossible to evacuate.
00:46:59
The machine is stuck in a ground that collapses on top of it.
00:47:05
- We got stuck in this loophole and we excavated without moving forward.
00:47:09
We tended to empty the mountain.
00:47:10
If we were in an urban environment, it would have been a real disaster.
00:47:14
The cutting wheel was immobilized, to treat the ground,
00:47:17
it was necessary to empty each arm from the wheel to the hand.
00:47:19
And I remember very good teams,
00:47:21
with shovel and bucket to drain the cutting wheel.
00:47:27
This blockage is a challenge for engineers,
00:47:29
but their mission is to confront to all the difficulties
00:47:33
and invent new solutions.
00:47:40
Firstly, the wheel located at the front is moved back a few meters,
00:47:44
to arrange spaces intervention for technicians,
00:47:47
which start with butcher side openings,
00:47:49
in order to limit the quantity of material to be evacuated.
00:47:55
In a second time, geological survey tools,
00:47:58
are used to sink into the rock over several tens of meters
00:48:01
and inject grout into it cement and resin,
00:48:05
which makes it possible to consolidate the area above
00:48:07
and in front of the tunnel boring machine.
00:48:11
- We reconstructed a homogeneous whole,
00:48:14
who allowed us to tear up materials
00:48:17
while maintaining a certain peripheral stability.
00:48:22
It took a total of 4 months to adapt the machine to the terrain,
00:48:25
then adapt the terrain to the machine.
00:48:32
This experience will be good useful to the eight tunnel boring machines,
00:48:34
who will perceive the two galleries 57.5 kilometers,
00:48:38
of the future Lyon-Turin tunnel.
00:48:43
During 4 years of work,
00:48:45
permanent adaptation techniques were necessary,
00:48:48
to dig without being blocked,
00:48:49
but also at each stage of this construction site,
00:48:52
of exceptional scale.
00:48:59
In the cockpit in September 2019,
00:49:02
tension and excitement are palpable.
00:49:06
These men and women arrive at end of their reconnaissance mission.
00:49:11
Only a few centimeters left.
00:49:14
- Breakthrough is a very important since our job,
00:49:17
it's a profession of passion, of commitment.
00:49:19
We finish the match, it's the final whistle.
00:49:22
Suddenly, there is an explosion of joy.
00:49:26
On the other side, the wheel breaks the rock
00:49:28
and appears with a bang.
00:49:34
Mission accomplished for the teams who, as tradition dictates,
00:49:37
slide through the structure,
00:49:39
to get out into the open air, one by one.
00:49:44
- We completed these 9 kilometers in three years,
00:49:46
in difficult terrain, with risks,
00:49:49
which were objectively very important.
00:49:53
So it's a success down the line.
00:49:56
- We encountered difficulties, we crossed them,
00:49:59
what makes merit even more important.
00:50:01
I am proud of the teams who designed the machine,
00:50:04
she fulfilled her mission.
00:50:06
And I am extremely proud of the teams formed
00:50:09
and who succeeded a tremendous feat.
00:50:13
After four years of work,
00:50:15
these women and men tested all technologies
00:50:18
allowing you to defeat one of the massifs the most complex on the planet.
00:50:23
Their success paves the way for one the most ambitious projects,
00:50:26
of the next few years.
00:50:29
By 2030, 7 tunnel boring machines like Federica,
00:50:33
should come into action.
00:50:35
Nearly 2,000 miners could dig and solidify,
00:50:37
the galleries relentlessly to build a megastructure,
00:50:40
as colossal as it is strategic,
00:50:43
the Lyon-Turin tunnel will be the longest in the world.

Description:

Durante milenios, los túneles nos han permitido acortar distancias y salvar obstáculos considerados infranqueables. Hoy, en el corazón de los Alpes, cientos de hombres y mujeres ponen sus conocimientos al servicio de un proyecto titánico: construir el túnel ferroviario más grande del mundo: el Lyon-Turín. Dentro de una colosal obra de construcción, estos constructores inventan y utilizan todas las técnicas para superar la montaña y construir la obra del siglo. Director: Quentin Domart y Hugo Hernández

Preparing download options

popular icon
Popular
hd icon
HD video
audio icon
Only sound
total icon
All
* — If the video is playing in a new tab, go to it, then right-click on the video and select "Save video as..."
** — Link intended for online playback in specialized players

Questions about downloading video

mobile menu iconHow can I download "El túnel más grande del mundo: mineros frente a las montañas" video?mobile menu icon

  • http://unidownloader.com/ website is the best way to download a video or a separate audio track if you want to do without installing programs and extensions.

  • The UDL Helper extension is a convenient button that is seamlessly integrated into YouTube, Instagram and OK.ru sites for fast content download.

  • UDL Client program (for Windows) is the most powerful solution that supports more than 900 websites, social networks and video hosting sites, as well as any video quality that is available in the source.

  • UDL Lite is a really convenient way to access a website from your mobile device. With its help, you can easily download videos directly to your smartphone.

mobile menu iconWhich format of "El túnel más grande del mundo: mineros frente a las montañas" video should I choose?mobile menu icon

  • The best quality formats are FullHD (1080p), 2K (1440p), 4K (2160p) and 8K (4320p). The higher the resolution of your screen, the higher the video quality should be. However, there are other factors to consider: download speed, amount of free space, and device performance during playback.

mobile menu iconWhy does my computer freeze when loading a "El túnel más grande del mundo: mineros frente a las montañas" video?mobile menu icon

  • The browser/computer should not freeze completely! If this happens, please report it with a link to the video. Sometimes videos cannot be downloaded directly in a suitable format, so we have added the ability to convert the file to the desired format. In some cases, this process may actively use computer resources.

mobile menu iconHow can I download "El túnel más grande del mundo: mineros frente a las montañas" video to my phone?mobile menu icon

  • You can download a video to your smartphone using the website or the PWA application UDL Lite. It is also possible to send a download link via QR code using the UDL Helper extension.

mobile menu iconHow can I download an audio track (music) to MP3 "El túnel más grande del mundo: mineros frente a las montañas"?mobile menu icon

  • The most convenient way is to use the UDL Client program, which supports converting video to MP3 format. In some cases, MP3 can also be downloaded through the UDL Helper extension.

mobile menu iconHow can I save a frame from a video "El túnel más grande del mundo: mineros frente a las montañas"?mobile menu icon

  • This feature is available in the UDL Helper extension. Make sure that "Show the video snapshot button" is checked in the settings. A camera icon should appear in the lower right corner of the player to the left of the "Settings" icon. When you click on it, the current frame from the video will be saved to your computer in JPEG format.

mobile menu iconWhat's the price of all this stuff?mobile menu icon

  • It costs nothing. Our services are absolutely free for all users. There are no PRO subscriptions, no restrictions on the number or maximum length of downloaded videos.